Spain awards €56.1 million for three hybrid battery projects
Spain’s Ministry for the Ecological Transition and the Demographic Challenge (MITECO) has allocated €56.1 million to three BESS projects developed by Iberdrola Renovables Andalucía in the province of Granada. The facilities, named BAT Huéneja, BAT Dólar 3 and BAT Ferreira 2, will be hybridized with renewable energy generation installations in the municipalities of Huéneja, Dólar and Ferreira.
The grants come from the first call for innovative energy storage projects under the PINALM program, co-funded by the European Regional Development Fund (ERDF) for 2021–2027. The three projects were initially placed on a waiting list after the call’s results were announced in December 2025. The withdrawal of two previously selected Andalusian beneficiaries freed up €56,099,575, which has now been reassigned to the first three eligible projects on the regional waiting list.
Each battery will have 44.5 MW of power capacity and 183.94 MWh of storage capacity. Together, the three projects will provide 133.5 MW and 551.82 MWh.
BAT Huéneja, listed under application number FEDER-PINALM-2025-002228, will receive €20.42 million. BAT Dólar 3, application FEDER-PINALM-2025-002255, will also receive €20.42 million. BAT Ferreira 2, application FEDER-PINALM-2025-002256, has initially been allocated €15.26 million. Each project has eligible costs of €40.49 million and received a score of 87 points. The grant for BAT Ferreira 2 could increase to €20.42 million if either of the two projects ranked ahead of it declines the full grant or fails to meet the requirements.
Wind and solar
The three storage projects are linked to Iberdrola renewable energy developments in the same area of Granada.
BAT Huéneja will be hybridized with the Huéneja 3 wind farm and the planned HIB Huéneja 3 solar plant. The solar project has 49.4 MW of installed capacity and 58.44 MWp of peak capacity. It will comprise 108,229 modules rated at 540 Wp, 13 inverters rated at 3.8 MW each and a fenced area of 96.2 hectares. The existing Huéneja 3 wind farm has 49.5 MW of installed capacity. The solar plant is planned to connect through three underground 30 kV circuits to the S1 Huéneja 30/220 kV substation, which is connected to Red Eléctrica’s Huéneja 400/220 kV substation.
BAT Dólar 3 is associated with the Hibridación Dólar 3 solar plant and the Dólar 3 wind farm, both owned by Iberdrola Renovables Andalucía. The solar project has 43.973 MWp of peak capacity and 36.9 MW of installed capacity. It will comprise 81,432 modules rated at 540 Wp, 2,808 fixed structures and 12 inverters rated at 3,075 kW each. Its fenced area covers 49.63 hectares. The Dólar 3 wind farm, commissioned in 2007, has 49.5 MW of installed capacity. The solar plant connects through three underground 30 kV circuits to the HIB Huéneja 30/220 kV substation.
BAT Ferreira 2 is linked to the HIB Ferreira 2 hybrid installation, which has 38.74 MW of installed solar capacity, and the Ferreira 2 wind farm, with 49.5 MW. The wind farm comprises 25 turbines rated at 2 MW each and entered operation in 2007. The solar plant occupies 54.14 hectares and uses fixed structures and power blocks comprising four 5,960 kW units and five 2,980 kW units. Its grid connection uses two underground 30 kV circuits to the HIB Huéneja 30/220 kV substation.
The three solar projects – Huéneja 3, Dólar 3 and Ferreira 2 – form part of a group of Iberdrola hybrid installations that share some grid connection infrastructure. The HIB Huéneja 30/220 kV substation collects electricity from the Dólar I, Dólar III and Ferreira II plants, while Huéneja III connects to the Huéneja infrastructure. Electricity is then evacuated through a 220 kV line to the Huéneja S1 400/220/30 kV substation, located next to Red Eléctrica’s existing substation. The planned line comprises a 15.224 km overhead section and an underground section of approximately 293 meters.
The €56.1 million allocation follows the withdrawal of two projects that had initially been awarded funding in Andalusia. Their combined withdrawal freed up €56,099,575, allowing the three Iberdrola projects at the top of the regional waiting list to receive grants.
With this latest allocation, the PINALM program has awarded €826 million to 130 energy storage projects. Once completed, they are expected to provide a combined 2.2 GW of power capacity and 9.4 GWh of storage capacity. The call received more than 1,700 applications, and its initial €700 million budget was increased by 17%. Awarded projects must be completed by Dec. 31, 2029.