Italian merchant battery capital costs could hit 14.6% if yields rise

An Italian consultancy says regulatory uncertainty and a lack of public data on deal terms are raising financing costs for battery storage. It argues that fixed auction calendars and market transparency would cost far less than the risk premium investors now charge.
Image: FRV

Battery projects in Italy that sell only into the market would see their average cost of capital rise from 12.1% to 14.6% if government bond yields increased by two percentage points, according to a simulation by consultancy PTS. Over the same shift, projects with contracts under MACSE, Italy’s storage capacity procurement mechanism, would go from 8.8% to 11%.

The estimates come as investors reassess the Italian market amid talk of a possible European Central Bank rate hike in December. PTS said regulatory uncertainty raises project risk for every investor. Combined with what it called “a system risk,” it could drive smaller investors out of the market and reduce competition in auctions. PTS estimates that MACSE contracts lower the cost of capital by 32% to 38% compared with merchant projects, with Italy’s capacity market sitting in between.

pv magazine Italy spoke with Nina Però and Paolo Verna, partners at PTS, a strategy, operations and financial advisory group founded in 1995.

Cost of capital is a major driver of storage deployment. What are the main trends caused by external factors such as interest rates?

Verna: The first is interest rates. Banks and investors start from government bond yields and add a premium for risk. If rates rise, everything rises. In a PTS simulation, a two-point increase in government bond yields would take the cost of capital from 8.8% to 11% for a project with a MACSE contract, and from 12.1% to 14.6% for one that sells only on the market. The gap between the two would widen, so reducing risk matters even more when rates are high. The spread between Italian and German government bonds also weighs, as does inflation, which reduces the real value of fixed-price contracts.

Your estimates, based on market parameters at the end of October 2026, put the average cost of capital at about 8.8% for a MACSE project and 12.1% for a merchant one. You say the gap reflects almost entirely the risk premium, not the financial structure. On a €100 million ($109.4 million) investment, the merchant project must generate about €2.5 million more in revenue each year, or nearly €38 million over 15 years. Do power purchase agreements also lower the cost of capital?

Verna: Yes, because they turn uncertain revenue into guaranteed revenue, and banks lend more, at a lower cost, to borrowers with secure income. For batteries, these contracts usually take the form of a tolling agreement, in which an operator pays a fixed fee to use the battery. The benefit depends on how long the contract lasts and who the counterparty is. A tolling agreement typically runs five to 10 years, while the loan runs 15. For the years not covered, the bank treats the project as being as risky as one with no contract, and lends less.

What about the capacity market?

Verna: It sits halfway between MACSE and the merchant market. The contract lasts 15 years, but the amount of capacity paid for can be revised after signing, so the revenue is not entirely certain. That is why the projects financed so far have paired it with a tolling agreement. One proposal could be to freeze these revisions for contracts already signed, or limit them within known margins.

Do you have data on the average cost of capital by region?

Verna: No. The cost of capital depends mainly on how secure revenue is, not on where the plant is located. What changes from one zone to another is the potential revenue and the permitting timeline.

You have said that the cost of capital weighs as much as technology, but unlike cell prices it is largely decided in Italy, through rules and contracts. How does this vary across investors? Does an investment fund have less difficulty obtaining financing?

Verna: It has easier access to capital, but the project risk does not disappear. The fund still has to deliver a return to its own investors, and if the project is risky, that return will be higher. Rules and contracts, on the other hand, affect everyone. Anyone who invests is made to pay for regulatory uncertainty. There is also a system risk. If capital stays expensive for midsize operators, the market concentrates around large groups and competition in auctions declines.

You say each additional percentage point of weighted average cost of capital is worth about 6% of the revenue a plant must generate to pay for itself. How and why could that figure change?

Verna: The 6% shows how much the revenue needed to repay the plant rises for each additional point of cost of capital, over 15 years. The figure changes mainly with duration. The longer the repayment period, the more the cost of capital weighs. According to PTS estimates, one point is worth about 4.5% over 10 years and more than 7% over 20 years. It changes less with the level of interest rates and stays between 5% and 7% under current conditions.

You also discuss available funding. At the EU level, the Innovation Fund can cover up to 60% of relevant costs for innovative projects, the Battery Booster Facility has €1.5 billion in loans and InvestEU operates with a €26.2 billion EU guarantee. In Italy, development contracts under the “Net Zero, Renewables and Batteries” windows of the National Recovery and Resilience Plan (PNRR) had €1.74 billion available, at least €205 million of it for batteries. How important is it that these funds have long time horizons? Are there examples of best practice?

Però: It is important to be clear about which horizon we mean. Instruments such as the development contract finance the construction or expansion of a plant, with investment programs normally completed within 36 months, which is consistent with building a factory. The question of a long horizon arises on two other levels. The first is continuity. A company planning an investment in the battery supply chain needs to know the instrument will still exist, with stable rules, when its project is mature. Windows that open and close at short notice, as those tied to PNRR deadlines did, reward those who are already prepared but do not allow companies still building a solid project to plan. When the instrument is available and the project is well structured, results follow. One example is a project PTS advised on for the joint venture between ReneSys Energy Inc. and Intertoll. ReneSys Energy Co will build two micro-factories in Termoli for lithium-ion cells and energy storage systems. The project was approved by Invitalia under the Net Zero development contract, with a grant of more than €49 million from PNRR funds against an investment of more than €140 million. The second level is coverage of the full investment life cycle. After construction, complementary instruments are needed: ramp-up loans such as the Battery Booster Facility, debt guarantees and, on the demand side, mechanisms such as MACSE, whose 15-year contracts give visibility to the entire supply chain.

You also point to an information gap. Of the 25 transactions PTS tracked between 2024 and 2026, worth €3.1 billion including €1.3 billion of debt, only one disclosed its leverage. Could you elaborate?

Verna: Of those 25 transactions, only one disclosed how much of the investment was financed with debt. Acquisition prices are almost never disclosed, and bank debt does not appear in project companies’ accounts because it sits with the parent companies. The prices of some grid services are not published either. Without benchmarks, lenders protect themselves by adding a safety margin, and the system pays for that margin. That is why PTS proposes an anonymous observatory on financing terms and the publication of market data. These measures do not require public money.

Any other considerations?

Verna: The main message is that reducing risk costs less than paying for it. Some measures, such as publishing data and setting a firm auction calendar, can be launched within a few months at limited cost. PTS estimates are based on market data from the end of October 2026 and should be read as orders of magnitude.

From pv magazine Italia

Written by

  • Sergio Matalucci is a journalist and writer specializing in energy, geopolitics, and international relations. He has worked for Reuters, served as Western Europe correspondent for Natural Gas Europe, and was a senior editor at Ruptly. In addition to his position at pv magazine, he collaborates with several Italian and international publications, including Staffetta Quotidiana and Arte.

Comments

Your email address will not be published. Required fields are marked *

Cancel reply
Please enter your comment.
Please enter your name.

This website uses cookies to anonymously count visitor numbers. View our privacy policy.

The cookie settings on this website are set to "allow cookies" to give you the best browsing experience possible. If you continue to use this website without changing your cookie settings or you click "Accept" below then you are consenting to this.

Close